Here are a few scenes from the construction on the MapleHeart, the part that will link that trail to the Pumpkinvine. These photos are of the section between Oak Ridge Park and Main St., the part that was most challenging, since they had to go under the 3rd St. overpass. Construction of the MapleHeart Trail in Goshen It is possible that due to the rain they won't be finished by Nov. 1.
I asked one of the workers about the gravel section between Main St. and the Pumpkinvine, and she said that it would remain gravel until the city finished some sewer work in that area. But it is rideable surface. I met three bikers on it earlier in the week.